Annex I

Projected Resource Requirements for Korean Remains

Phase II


KOREAN WAR REMAINS IDENTIFICATIONS PROJECTIONS

PHASE II

ASSUMPTIONS:

1) 3000 SETS OF REMAINS

2) 4 BONE SAMPLES PER SET OF REMAINS

3) DNA TESTING PERSONNEL 50% INCREASED EFFICIENCY

MARGINAL COSTS:

1) LABOR COSTS

2) SUPPLIES & REAGENTS

FIXED COSTS:

$1,050,000 FOR LEASE & UTILITIES

$140,868 FOR 3 ADMINISTRATIVE PERSONNEL

$102,874 FOR 5 YEAR AMORTIZED INSTRUMENTS & EQUIPMENT COSTS

$50,000 FOR MAINTENANCE AGREEMENTS

$1,343,742 PER YEAR

OPTION 1

Duration in Years --------------------------- 8

Number of Case Yearly -------------------- 375

Total Laboratory Personnel Needed --------- 42

First Year Total Cost ------------------- $ 5,855,942

Total Labor Cost ----------------------- $26,143,974

Total Marginal Cost -------------------- $39,943,974

Total Project Cost ---------------------- $50,693,910

OPTION 2 Duration in Years --------------------------- 10

Number of Case Yearly -------------------- 300

Total Laboratory Personnel Needed --------- 33

First Year Total Cost ------------------- $ 4,961,542

Total Labor Cost ----------------------- $27,498,555

Total Marginal Cost -------------------- $38,538,555

Total Project Cost ---------------------- $51,975,975

OPTION 3 Duration in Years --------------------------- 12

Number of Case Yearly -------------------- 250

Total Laboratory Personnel Needed --------- 28

First Year Total Cost ------------------- $ 4,961,542

Total Labor Cost ----------------------- $28,803,306

Total Marginal Cost -------------------- $38,003,306

Total Project Cost ---------------------- $54,128,210